Magnusson’s Dispute Resolution team summarises some of the most interesting and notable Supreme Court decisions from 2026. We examine, among other things, acknowledgements of debt that interrupt limitation periods, jurisdiction in cross-border contractual disputes, the scope of the material that courts may consider in civil proceedings where the parties control the subject matter of the dispute, and the burden and standard of proof when assessing hypothetical scenarios in damages claims.

Supreme Court decision NJA 2026 p. 42, “Dödsbodelägarens preskriptionsavbrott” (Interruption of the limitation period by an estate beneficiary)

Determining when a debtor has acknowledged a debt is a central issue in the law of limitation. As a general rule, a claim becomes time-barred ten years after it arises. However, the limitation period may be interrupted if the debtor acknowledges the claim, in which case a new limitation period begins to run from the date of interruption.

The question in this case was whether the inclusion of a debt in an estate inventory constitutes an acknowledgement of the claim by the debtor towards the creditor. The Swedish Supreme Court (the “Supreme Court”) held that an acknowledgement must be directed towards the creditor in order to interrupt the limitation period. For example, no interruption occurs where a debtor records a debt in a document that is not intended for the creditor.

The inclusion of a debt in an estate inventory does not, in itself, interrupt the limitation period, as the acknowledgement cannot generally be regarded as directed towards the creditor. The Supreme Court emphasised that estate inventories are primarily intended for estate beneficiaries and people entitled to inherit subsequently, rather than creditors.

The assessment may, however, be different if the creditor belongs to the group of people for whom the estate inventory is intended and the debt is recorded without reservation. In such circumstances, the creditor should be considered to have reasonable grounds to assume that the debtor accepts liability for the debt. The debtor is then deemed to have acknowledged the claim towards the creditor, thereby interrupting the limitation period. It is immaterial whether a creditor belonging to that group attended the estate inventory proceedings.

The decision has practical significance for estate beneficiaries and people entitled to inherit subsequently who have a claim against the deceased. For these creditors, the inclusion of a debt in an estate inventory without reservation may be relevant not only as a record of the claim but also in determining whether the limitation period has been interrupted. It is therefore important to ensure that the claim is accurately recorded, as this may trigger a new limitation period.

Supreme Court decision NJA 2026 p. 170, “Den polska byggnadsställningen” (The Polish scaffolding)

Cross-border contractual relationships frequently give rise to questions of jurisdiction and the appropriate forum for resolving disputes.

This case concerned whether a Swedish court had jurisdiction to hear a dispute relating to the sale of goods where the defendant was domiciled in another EU Member State and the place of delivery could not be determined from the contract, but the buyer had obtained actual control of the goods at a location in Sweden.

A Swedish company had purchased scaffolding from a Polish company. The scaffolding was transported from Poland to Örebro by an independent carrier. The contract did not specify a place of delivery. A dispute arose when the claimant alleged that the scaffolding was defective.

Jurisdiction is governed by the Brussels I Regulation, under which the general rule is that proceedings must be brought before the courts of the Member State in which the defendant is domiciled. In contractual matters, however, proceedings may be brought before the courts of the place of performance. In the case of a sale of goods, this is the place where, under the contract, the goods were delivered or should have been delivered.

Applying the case law of the Court of Justice of the European Union on the autonomous interpretation of the concept of the place of delivery, the Supreme Court held that the decisive factor is the place where the goods are physically handed over to the buyer and where the buyer obtains actual control of them. Örebro was therefore found to be the final place of delivery, and Örebro District Court was held to have jurisdiction to hear the dispute.

The question of which court has jurisdiction can have significant practical and financial implications. It is important for parties to specify the place of delivery in their contracts. Where the contract does not contain such a provision, the parties’ actual conduct becomes relevant to the assessment. The relevant place of delivery is where the buyer obtains actual control of the goods at their final destination. The place where the goods are handed over to an independent carrier is not decisive.

Supreme Court decision NJA 2026 p. 216, “Vindsvåningen” (The attic apartment)

In civil proceedings where the parties control the subject matter of the dispute, the parties are responsible for presenting the material on which the court is to base its decision. Parties may introduce documents as part of their presentation of the facts, rather than formally relying on them as evidence.

In this case, the claimant had submitted documents in this manner. However, the Court of Appeal disregarded them on the grounds that they had not been formally relied upon as evidence and therefore could not form the basis for determining disputed facts of legal significance. The Supreme Court was consequently required to decide whether the Court of Appeal’s failure to consider the documents constituted a procedural error.

The Supreme Court began by emphasising that a court must determine what has been proven in a case following a conscientious assessment of the material before it. The court’s obligation to consider a particular circumstance does not depend on whether it has been introduced through material expressly relied upon as evidence. Instead, the decisive factor is whether the circumstance has been introduced into the proceedings in such a way that it forms part of the material before the court.

Against this background, the Supreme Court found that the Court of Appeal had committed a procedural error by disregarding the documents. The fact that the documents could instead have been formally relied upon as evidence did not alter this conclusion. The procedural error was considered to be of such nature that it could be assumed to have affected the outcome of the case.

The Supreme Court also addressed the extent of a court’s responsibility to clarify how documents should be classified for procedural purposes. As part of its case management responsibilities, a court may have reason to encourage a party to rely formally on a document as evidence rather than merely presenting it as part of its account of the facts. However, this should not be understood as imposing a general duty on the court to classify documents submitted by the parties.

The decision clarifies that the material a court may consider in civil proceedings of this kind is not limited to documents formally relied upon as evidence. Documents introduced as part of a party’s presentation of the facts must also be considered.

This is particularly relevant in cases involving extensive written documentation, such as contracts, supplementary agreements, invoices, email correspondence and other records. Nevertheless, there are several procedural advantages to formally relying on documents as evidence and clearly identifying the facts that each document is intended to prove. The Supreme Court also provides guidance on how parties should present their evidence (see in particular paragraph 14 onwards of the judgment).

Supreme Court decision T 8371–24, 9 July 2026, “Innovationen” (The innovation)

In cases of breach of contract, the injured party is generally entitled to damages reflecting the positive contractual interest, meaning that the party should be placed in the same financial position as if the contract had been performed.

Establishing what would have happened had a breach of contract not occurred can present considerable difficulties. This issue was central to the present case, in which the Supreme Court was required to establish a hypothetical sequence of events to assess liability for damages arising from a breach of contract. The case also raised questions concerning the burden and standard of proof.

The dispute arose after a couple withdrew from the purchase of an apartment and entered into a termination agreement with the tenant-owner association. Under the agreement, the association was to grant the right to the apartment to another purchaser, while the couple would be liable for any losses incurred by the association.

However, in breach of the termination agreement, the association allowed the new purchaser to take possession of the apartment without paying for it. The new purchaser subsequently sold the apartment at a lower price. The couple brought a claim for damages against the association, arguing that it had breached the termination agreement by allowing the purchaser to take possession without payment.

The Supreme Court acknowledged the difficulties inherent in assessments involving hypothetical scenarios. The fundamental problem is that it is impossible to prove how a person would have acted in circumstances other than those that actually occurred. In such assessments, what can be proven are the circumstances underlying assumptions about how events might have unfolded.

In damages claims, the general rule is that the relevant facts must be proven and that the burden of proof rests with the party claiming to have suffered a loss. However, depending on the parties’ respective opportunities to obtain and preserve evidence, there may be grounds for reversing the burden of proof or lowering the standard of proof.

The Supreme Court emphasised that the mere presence of a hypothetical element does not, in itself, justify relaxing the evidential requirements.

In the present case, the new purchaser’s ability to pay at the time of taking possession was central to the assessment. The couple did not become aware that the right to the apartment had been granted until almost two years later and had therefore lost the opportunity to obtain and preserve evidence at the relevant time. The Supreme Court found that the burden of proof should remain with the couple but that the standard of proof should be lowered.

The decision provides valuable guidance on evidential issues arising when assessing hypothetical scenarios in damages claims. The fact that an assessment involves a hypothetical element does not automatically justify a lower standard of proof, but nor does it preclude a relaxation of the evidential requirements where the circumstances warrant it.

Parties seeking damages for breach of contract should pay particular attention to the opportunities each party has had to obtain and preserve evidence.

Supreme Court decision T 2545–25, 9 September 2026, “Bilbranden i Malmö” (The car fire in Malmö)

The case concerned a dispute over insurance compensation between a policyholder and If Skadeförsäkring AB. The policyholder’s car had been completely destroyed in a fire deliberately started by a third party. If refused to pay compensation, citing the risk that its employees could thereby commit the offence of commercial money laundering.

The question was under what circumstances an insurance company may refuse to pay insurance compensation on this ground.

The Supreme Court found that the policyholder was, in principle, entitled to compensation for the loss. Once an insurance company has accepted that an insured event has occurred, the starting point is that it has a contractual obligation to pay compensation.

However, If argued that there were reasonable grounds to assume that the policyholder had claimed compensation for the purpose of concealing that the insured vehicle was derived from crime or criminal activity.

The policyholder maintained that the circumstances surrounding the fire should not be taken into account, as the insurance company had already accepted that an insured event had occurred.

The Supreme Court held that an insurance company’s acceptance that an insured event has occurred does not mean that it has acknowledged any factual circumstances relating to the fire.

The Supreme Court concluded that, based on an objective assessment from the insurance company’s perspective, there were reasonable grounds to assume that the claim for compensation had been made for money laundering purposes.

The circumstances were sufficiently serious and involved risks of such a nature that making a payment would constitute culpable risk-taking on the part of the insurance company. The employees handling the claim must also have been aware of these circumstances. Accordingly, if a payment were made, their intent would encompass the circumstances that rendered the risk-taking culpable.

The decision highlights the importance of insurance companies thoroughly investigating and assessing the circumstances of each individual case before deciding whether to pay insurance compensation.

 